Sea trials and handover: how a refit ends well
The last days of a refit decide how the first season goes. How to plan the trial, what to test under load, what to receive at handover and why the follow up visit matters.
Early on a still morning, the yacht slips her lines for the first time in months. On deck, the captain watches the quay fall away; below, two engineers from the yard crouch in the engine room with a torch, a notebook and an infrared thermometer. The smell of new paint still hangs in the saloon. Everyone is a little nervous, and rightly so. The sea trial is the moment when months of work meet the conditions they were built for, and how it is planned decides how much it reveals.
Ready at the quay before going to sea
A good sea trial begins with a written trial plan, agreed with the yard well before the day. It lists every system to be tested, the conditions needed, the readings to be taken and who is responsible for each item. Before the yacht leaves the quay, every system should already have been commissioned alongside: engines run and checked, electrics live and tested, electronics switched on and configured, pumps and plumbing proven, steering moved through its full range. The sea trial is for confirming performance under way, not for discovering that something was never connected.
Check that the safety gear is aboard and in date, that there is enough fuel for a full load run and that the weather suits the tests. Agree who will be aboard: usually the yard’s project manager and engineers, the captain and crew, and, if you have one, your surveyor or project manager. Keep the number of guests small; a sea trial is work, not a celebration.
The trial plan in practice
The exact content depends on the yacht and the work done, but most trials after a substantial refit cover the following items.
| System | What to confirm on the trial |
|---|---|
| Engines | Full load run to the rated revolutions; oil pressure, coolant and exhaust temperatures, exhaust appearance and cooling water flow |
| Speed | Speed against revolutions over a measured run in both directions, compared with earlier records where available |
| Steering | Lock to lock at speed and at low revolutions, with no binding, noise or play |
| Autopilot | Calibration under way, holding a course in each mode used on board |
| Generators | Running under a realistic electrical load for a sustained period |
| Thrusters and stabilisers | Function, response and control from every station |
| Anchoring gear | Windlass, chain, brake and anchor stowage, with a real anchoring |
| Bilge pumps | Every pump and float switch, with alarms tested |
| Navigation electronics | Displays, radar, AIS, instruments and network data shared correctly |
| Sails and rig | On sailing yachts, sails hoisted and the rig loaded in a good breeze |
Engines at full load
An engine that reaches its rated revolutions under full load proves that it, the gearbox and the propeller are matched to the hull. If it falls short, the propeller may be wrong, the hull may be fouled, or the engine may have a problem; if it overspeeds, the propeller may be too small. Hold the full load long enough for temperatures to settle, and record oil pressure, coolant temperature, exhaust temperatures where measured, and the colour and volume of the exhaust. After the run, the engineers will look over the engine room for leaks and loose fittings, because heat and vibration find every weak connection.
Steering, autopilot and manoeuvring
Steering is tested from lock to lock at speed and at low revolutions, listening and feeling for binding, noise or play. The autopilot needs calibration under way, which often takes longer than expected: compass calibration, rudder settings and a test of each mode you will use. Thrusters and stabilisers are tried in realistic conditions, and the yacht should be manoeuvred alongside a quay at least once, because that is where many small faults in controls first show themselves.
Sailing yachts: the rig under load
A rig cannot be judged at the quay. On a sailing yacht, the trial should include a proper sail in a good breeze, with every sail hoisted, reefed and furled, the rig tuned under load, and a close look at chainplates, deck fittings and the mast step from below while the boat is heeled. Leaks around newly bedded fittings often appear only when the deck is wet and working.
A fault found on the sea trial is a gift; the same fault found on the first night passage is a story nobody wanted to tell.
Writing it all down
Note every fault on the snag list during the trial itself, not afterwards from memory. Record where it happened, under what conditions and with what readings, and take photographs or short videos where they help. A noise at certain revolutions, a drip that appears after twenty minutes, an instrument that loses data when the radar transmits: details like these make the difference between a quick fix and a long search. Agree with the yard at the end of the day which items they will address before handover and which may need a second trial.
Handover: what you should receive
Handover is the formal end of the refit, and it deserves a checklist of its own. Do not accept the yacht until the essentials are in your hands:
- A completed snag list, with each item closed or formally agreed for later.
- Updated manuals and diagrams for every system that was changed.
- Warranty documents, with start dates and conditions.
- Keys, codes, tools and the spare parts agreed in the specification.
- A walk through of the yacht with the crew or owner, system by system.
Shakedown cruise and the follow up visit
Plan a short shakedown cruise before the first long passage or the first guests. A few days of normal use bring out things no trial can: a locker that rattles, a pump that cycles, a fitting that weeps in a following sea. Agree a follow up visit with the yard after the first weeks, when small leaks and loose fittings show up as the yacht settles into use. Report everything in writing within the warranty period, and a refit that ended well on the day of handover will stay that way through the season.
Questions and answers
Who should be aboard for a sea trial after a refit?
Usually the yard’s project manager and engineers, the captain and crew, and the owner’s surveyor or project manager if there is one. Keep guests to a minimum, because the trial is working time.
What does it mean if an engine does not reach its rated revolutions?
It suggests a mismatch or a problem: the propeller may be too large, the hull may be fouled, or the engine may not be delivering its power. The cause should be found before handover.
Can I accept the yacht with open snag list items?
Yes, if each open item is formally agreed in writing with the yard, with a date for completion. Open items without agreement are easily forgotten once the yacht has left.
Why is a follow up visit useful?
Some faults only appear after weeks of use, when heat, vibration and motion have worked on new installations. A planned visit within the warranty period lets the yard put them right.
Further reading in our network
- RanerisSuperyachts and charter
Superyachts and charter, with a look at how larger yachts return to service after their yard periods.
Our articles are general information written with care. Intervals and figures are guide values; the maker’s manual, your flag state, classification society and insurer take precedence, and safety critical work belongs with qualified professionals.